Viewing as

Teaching this? The teacher view adds 2 files, the mark schemes and the model answers.

Maths · Probability

Independent events and tree diagrams

Recognise independent events, multiply probabilities along the branches of a tree diagram, and add the probabilities of the outcomes you want.

  • 6 key terms
  • All boards
Download the full pack · 3 files

Warm-up

Answer each one, then check.

  1. 1

    Work out \(\dfrac{3}{5} \times \dfrac{3}{5}\).

    Show answerHide answer

    \(\dfrac{9}{25}\)

  2. 2

    Work out \(0.2 \times 0.8\).

    Show answerHide answer

    0.16

  3. 3

    What is \(1 - 0.2\)?

    Show answerHide answer

    0.8

  4. 4

    Work out \(\dfrac{9}{25} + \dfrac{4}{25}\).

    Show answerHide answer

    \(\dfrac{13}{25}\)

  5. 5

    What do all the probabilities on a set of branches add up to?

    Show answerHide answer

    1

Learning Objectives

  1. 1Recognise independent events.
  2. 2Use \(P(A \text{ and } B) = P(A) \times P(B)\) for independent events.
  3. 3Draw and complete a tree diagram.
  4. 4Use a tree diagram to find the probability of combined events.

INDEPENDENT EVENTS

Two events are independent if the outcome of one does not affect the outcome of the other.

For independent events, \(P(A \text{ and } B) = P(A) \times P(B)\).

Multiplying Probabilities

The probability that Sam is late for school is 0.3. The probability that it rains is 0.5. These events are independent. Find the probability that Sam is late and it rains.

Show the solutionHide the solution
  1. 1 Independent events, so multiply \(0.3 \times 0.5\)
  2. 2 Work it out \(0.15\)

Answer0.15

Using a Tree Diagram

Two rules do all the work.

  1. 1 Draw the branches

    One set for each event, with the probability on each branch

  2. 2 Check

    The probabilities on each set of branches add up to 1

  3. 3 Multiply along the branches

    This gives the probability of each combined outcome

  4. 4 Add the outcomes you want

    If more than one outcome fits, add their probabilities

  5. 5 Check the total

    All the outcomes add up to 1

Two Counters with Replacement

A bag has 3 red and 2 blue counters. A counter is taken, its colour is noted and it is put back. A second counter is then taken. Find the probability that both counters are the same colour.

Show the solutionHide the solution
  1. 1 Both red \(\dfrac{3}{5} \times \dfrac{3}{5} = \dfrac{9}{25}\)
  2. 2 Both blue \(\dfrac{2}{5} \times \dfrac{2}{5} = \dfrac{4}{25}\)
  3. 3 Same colour means RR or BB, so add \(\dfrac{9}{25} + \dfrac{4}{25}\)

Answer\(\dfrac{13}{25}\)

Late Two Days

The probability that Amy is late for school on any day is 0.2, independent of other days. Find (a) the probability she is late on both of two days, (b) late on exactly one of the two days, (c) late on at least one day.

Show the solutionHide the solution
  1. 1 (a) Multiply \(0.2 \times 0.2 = 0.04\)
  2. 2 (b) Late then not late, or not late then late \(0.2 \times 0.8 + 0.8 \times 0.2 = 0.16 + 0.16 = 0.32\)
  3. 3 (c) Use the complement: never late is \(0.8 \times 0.8 = 0.64\) \(1 - 0.64 = 0.36\)

Answer(a) 0.04 (b) 0.32 (c) 0.36

Shortcut: At Least One

"At least one" is easier by subtraction.

  • Find the opposite

    "None" is the outcome where the event never happens.

  • Subtract from 1

    \(P(\text{at least one}) = 1 - P(\text{none})\).

  • Saves work

    You avoid adding many branches.

The Four Outcomes

The outcomes of a two-stage tree with replacement.

  • Red, Red

    Working: \(\dfrac{3}{5} \times \dfrac{3}{5}\). Probability: \(\dfrac{9}{25}\)

  • Red, Blue

    Working: \(\dfrac{3}{5} \times \dfrac{2}{5}\). Probability: \(\dfrac{6}{25}\)

  • Blue, Red

    Working: \(\dfrac{2}{5} \times \dfrac{3}{5}\). Probability: \(\dfrac{6}{25}\)

  • Blue, Blue

    Working: \(\dfrac{2}{5} \times \dfrac{2}{5}\). Probability: \(\dfrac{4}{25}\)

  • Total

    Probability: 1

Free Throws

A basketball player scores a free throw with probability 0.7, independently each time. She takes two throws. Draw a tree diagram and find the probability she scores (a) both (b) exactly one (c) none.

1. Draw the tree.

2. Multiply along branches.

3. Add the outcomes needed.

A good answer shows: (a) \(0.7 \times 0.7 = 0.49\). (b) \(0.7 \times 0.3 + 0.3 \times 0.7 = 0.42\). (c) \(0.3 \times 0.3 = 0.09\). The three add up to 1.

Can I...?

  1. 1Decide if events are independent.
  2. 2Multiply probabilities of independent events.
  3. 3Draw a two-stage tree diagram.
  4. 4Label the branches with probabilities.
  5. 5Multiply along a path.
  6. 6Add the outcomes I want.
  7. 7Use "1 minus" for at least one.
  8. 8Check the total is 1.

Summary & Exam Focus

  • Independent: \(P(A \text{ and } B) = P(A) \times P(B)\).
  • Multiply along the branches, add between outcomes.
  • The branches from a node add up to 1.
  • At least one \(= 1 -\) none.

Exam focus

The probability that Amy is late on any day is 0.2. Work out the probability that she is late on at least one of two days. (3 marks) (3 marks)

"At least one" means one minus none. Never late on both days is \(0.8 \times 0.8\).

Key terms

The vocabulary this lesson expects you to use. Each one is linked from the first place it appears above.

Independent
The outcome of one event does not change the other.
Tree diagram
A diagram showing the outcomes of events and their probabilities on branches.
Branch
A line on a tree diagram carrying a probability.
With replacement
Putting the item back before the next pick.
Combined event
Two or more events considered together.
Complement
The event "not A".

Practice questions

Have a go at each one before you open its answer.

  1. Question 1 Non-calculator 2 marks

    A and B are independent events. \(P(A) = 0.3\) and \(P(B) = 0.5\). Work out \(P(A \text{ and } B)\).

    Show answerHide answer

    Model answer

    \(0.3 \times 0.5 = 0.15\).

    Mark scheme

    • \(0.3 \times 0.5\) — M1
    • 0.15 — A1
  2. Question 2 Non-calculator 3 marks

    The probability that Amy is late for school on any day is 0.2. The tree diagram shows the probabilities for two days. Complete the tree diagram.

    A two-stage tree diagram for two days with Amy late or not late, where only the first-day probabilities are given.
    Show answerHide answer

    Model answer

    All four second-stage branches: Late 0.2 and Not late 0.8, after either first-day outcome.

    Mark scheme

    • Late branches 0.2 on day 2 — B1
    • Not late branches 0.8 on day 2 — B1
    • All four correct — B1
  3. Question 3 Non-calculator 2 marks

    Using the tree diagram, work out the probability that Amy is late on both days.

    Show answerHide answer

    Model answer

    \(0.2 \times 0.2 = 0.04\).

    Mark scheme

    • \(0.2 \times 0.2\) — M1
    • 0.04 — A1
  4. Question 4 Non-calculator 3 marks

    Using the tree diagram, work out the probability that Amy is late on exactly one of the two days.

    Show answerHide answer

    Model answer

    \(0.2 \times 0.8 + 0.8 \times 0.2 = 0.16 + 0.16 = 0.32\).

    Mark scheme

    • One correct product — M1
    • Adding the two paths — M1
    • 0.32 — A1
  5. Question 5 Non-calculator 3 marks

    Work out the probability that Amy is late on at least one of the two days.

    Show answerHide answer

    Model answer

    The probability of never being late is \(0.8 \times 0.8 = 0.64\). So \(P(\text{at least one}) = 1 - 0.64 = 0.36\).

    Mark scheme

    • \(0.8 \times 0.8\) — M1
    • \(1 - 0.64\) — M1
    • 0.36 — A1
  6. Question 6 Non-calculator 4 marks

    A bag contains 3 red counters and 2 blue counters. A counter is taken at random, its colour is noted and it is replaced. A second counter is taken. Work out the probability that the two counters are the same colour.

    Show answerHide answer

    Model answer

    \(P(RR) = \dfrac{3}{5} \times \dfrac{3}{5} = \dfrac{9}{25}\) and \(P(BB) = \dfrac{2}{5} \times \dfrac{2}{5} = \dfrac{4}{25}\). Together: \(\dfrac{13}{25}\).

    Mark scheme

    • \(\dfrac{3}{5} \times \dfrac{3}{5}\) — M1
    • \(\dfrac{2}{5} \times \dfrac{2}{5}\) — M1
    • Adding the two — M1
    • \(\dfrac{13}{25}\) — A1

Quick check

  1. Two independent events have probabilities 0.4 and 0.5. What is the probability of both?

    1. A0.9
    2. B0.1
    3. C0.2
    4. D0.45
    Show answerHide answer

    C: 0.2

    Multiply: \(0.4 \times 0.5 = 0.2\).

  2. On a tree diagram, the probabilities on the branches from one node add up to...

    1. A0
    2. B1
    3. C2
    4. D0.5
    Show answerHide answer

    B: 1

    They cover all the outcomes, so they sum to 1.

  3. To find the probability of a path on a tree diagram, you...

    1. AMultiply along the branches
    2. BAdd along the branches
    3. CSubtract them
    4. DDivide them
    Show answerHide answer

    A: Multiply along the branches

    Multiply the probabilities along the branches.

  4. When two outcomes both give the result you want, you...

    1. AMultiply them
    2. BIgnore one
    3. CSubtract them
    4. DAdd them
    Show answerHide answer

    D: Add them

    Add the probabilities of the outcomes.

  5. \(P(\text{late}) = 0.2\). What is the probability of not being late twice in a row?

    1. A0.4
    2. B0.16
    3. C0.64
    4. D0.96
    Show answerHide answer

    C: 0.64

    \(0.8 \times 0.8 = 0.64\).

  6. A coin is flipped three times. What is the probability of three heads?

    1. A\(\dfrac{1}{6}\)
    2. B\(\dfrac{1}{8}\)
    3. C\(\dfrac{3}{8}\)
    4. D\(\dfrac{1}{2}\)
    Show answerHide answer

    B: \(\dfrac{1}{8}\)

    \(\dfrac{1}{2} \times \dfrac{1}{2} \times \dfrac{1}{2} = \dfrac{1}{8}\).

Downloads

Free to keep, print and annotate.

Something here looks wrong?

Tell us what and we will go and look. It goes to whoever writes these pages, nobody else, and we do not ask who you are — so there is nothing to sign and nothing comes back to you.